patents.google.com

CN115081915A - Multi-operation area information real-time interconnection intelligent material supervision method and system - Google Patents

  • ️Tue Sep 20 2022
Multi-operation area information real-time interconnection intelligent material supervision method and system Download PDF

Info

Publication number
CN115081915A
CN115081915A CN202210787153.XA CN202210787153A CN115081915A CN 115081915 A CN115081915 A CN 115081915A CN 202210787153 A CN202210787153 A CN 202210787153A CN 115081915 A CN115081915 A CN 115081915A Authority
CN
China
Prior art keywords
information
truck
real
intelligent
acquiring
Prior art date
2022-07-05
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210787153.XA
Other languages
Chinese (zh)
Inventor
谢先铭
李锦平
谭锟嵛
李勇
任凝续
黄章雷
邹德志
林培雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Nansha Zhujiang Brewery Co ltd
Original Assignee
Guangzhou Nansha Zhujiang Brewery Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
2022-07-05
Filing date
2022-07-05
Publication date
2022-09-20
2022-07-05 Application filed by Guangzhou Nansha Zhujiang Brewery Co ltd filed Critical Guangzhou Nansha Zhujiang Brewery Co ltd
2022-07-05 Priority to CN202210787153.XA priority Critical patent/CN115081915A/en
2022-09-20 Publication of CN115081915A publication Critical patent/CN115081915A/en
Status Pending legal-status Critical Current

Links

  • 239000000463 material Substances 0.000 title claims abstract description 36
  • 238000000034 method Methods 0.000 title claims abstract description 32
  • 238000012790 confirmation Methods 0.000 claims abstract description 24
  • 238000004891 communication Methods 0.000 claims abstract description 18
  • 238000012545 processing Methods 0.000 claims abstract description 15
  • 238000005303 weighing Methods 0.000 description 28
  • 238000007726 management method Methods 0.000 description 22
  • 230000006872 improvement Effects 0.000 description 8
  • 230000008569 process Effects 0.000 description 7
  • 238000005516 engineering process Methods 0.000 description 4
  • 238000012544 monitoring process Methods 0.000 description 4
  • 238000005259 measurement Methods 0.000 description 3
  • CURLTUGMZLYLDI-UHFFFAOYSA-N Carbon dioxide Chemical compound O=C=O CURLTUGMZLYLDI-UHFFFAOYSA-N 0.000 description 2
  • 230000003442 weekly effect Effects 0.000 description 2
  • 241000209140 Triticum Species 0.000 description 1
  • 235000021307 Triticum Nutrition 0.000 description 1
  • 230000002411 adverse Effects 0.000 description 1
  • 230000009286 beneficial effect Effects 0.000 description 1
  • 229910002092 carbon dioxide Inorganic materials 0.000 description 1
  • 239000001569 carbon dioxide Substances 0.000 description 1
  • 230000008859 change Effects 0.000 description 1
  • 238000013500 data storage Methods 0.000 description 1
  • 230000007547 defect Effects 0.000 description 1
  • 230000000694 effects Effects 0.000 description 1
  • 239000011521 glass Substances 0.000 description 1
  • 230000008676 import Effects 0.000 description 1
  • 230000010354 integration Effects 0.000 description 1
  • 238000004519 manufacturing process Methods 0.000 description 1
  • 238000012986 modification Methods 0.000 description 1
  • 230000004048 modification Effects 0.000 description 1
  • 238000003825 pressing Methods 0.000 description 1
  • 230000001681 protective effect Effects 0.000 description 1
  • 230000001360 synchronised effect Effects 0.000 description 1

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/02Reservations, e.g. for tickets, services or events
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Human Resources & Organizations (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Traffic Control Systems (AREA)

Abstract

The invention provides a method and a system for supervising multi-operation-area information real-time communication intelligent materials, which comprises the following steps: when a truck arrives at a factory area, acquiring first information of the truck; when the truck reaches a cargo processing point, after the first information confirmation information is acquired, allowing cargo processing to be carried out; after the goods are processed, second information of the truck is obtained; and uploading the first information and the second information to an ERP management system when second information confirmation information is acquired. The method and the system automatically acquire the first information and the second information of the truck, avoid the information from being tampered, simultaneously upload the first information and the second information of the truck to the ERP system, and are combined with data in the ERP system, so that the goods are conveniently managed.

Description

多作业区信息实时联通智能物资监管方法及系统Multi-operation area information real-time interconnection intelligent material supervision method and system

技术领域technical field

本发明属于物资管理技术领域,具体涉及多作业区信息实时联通智能物资监管方法及系统。The invention belongs to the technical field of material management, and in particular relates to a method and a system for real-time communication of information in multiple operation areas for intelligent material supervision.

背景技术Background technique

在生产企业中,通过需要运输物料进厂或者将废料运送离场,但在物资出入厂管理上,目前所采用的出入厂管理模式:车辆进厂登记、压驾驶证;车辆地磅称重,人工登记车牌,记录录入地磅显示的重量,绑定相关入场信息;车辆下地磅进入作业区,作业人员开单装卸货,人工填写车牌、业务公司、物资类型、数量(称重物资不填)、人员签名;车辆离开作业区上地磅第二次称重,人工手工记录相关信息,门岗核算员统计记录,核算,确定最终作业单;车辆出厂完成。上述模式,全部需要人工统计记录,车辆地磅无防护措施(仅称重,无防作弊系统);工作人员记录易出错,车牌记错、数据记错,与司机勾结改数据,作业单易丢失,数据无法追溯验证,不法人员地磅遥控作弊等风险,对公司物资管理造成很大隐患。同时,信息需输入电脑,月底才上报,信息较滞后。对公司资产管理造成不利影响。In production enterprises, materials need to be transported into the factory or scraps are transported away from the factory, but in the management of materials entering and leaving the factory, the current management mode of entering and leaving the factory: vehicle entering the factory registration, pressing the driver's license; vehicle weighing scales, manual labor Register the license plate, record and enter the weight displayed on the weighbridge, and bind the relevant admission information; the vehicle gets off the weighbridge and enters the operation area, the operator bills the loading and unloading, and manually fills in the license plate, business company, material type, quantity (weighing material is not filled), Personnel signature; the vehicle leaves the operation area and weighs the platform for the second time, manually records the relevant information, and the gatekeeper makes statistics and records, calculates, and determines the final work order; the vehicle leaves the factory. All of the above modes require manual statistics and records, and the vehicle weighbridge has no protective measures (only weighing, no anti-cheating system). The data cannot be verified retrospectively, and the risks such as illegal remote control cheating of the weighbridge have caused great hidden dangers to the company's material management. At the same time, the information needs to be entered into the computer, and it will be reported at the end of the month, and the information is lagging behind. adversely affect the company's asset management.

发明内容SUMMARY OF THE INVENTION

为了克服上述技术缺陷,本发明第一个方面公开了一种多作业区信息实时联通智能物资监管方法,包括步骤:In order to overcome the above-mentioned technical defects, a first aspect of the present invention discloses a real-time intelligent material monitoring method for multi-operation area information communication, including the steps:

货车到达厂区时,获取货车的第一信息;When the truck arrives at the factory, obtain the first information of the truck;

货车达到货物处理点时,在获取到第一信息确认信息后,被允许进行货物处理;When the truck reaches the cargo handling point, it is allowed to process the cargo after obtaining the first confirmation information;

在货物处理完毕后,获取货车的第二信息;After the goods are processed, obtain the second information of the truck;

在获取到第二信息确认信息时,将所述第一信息、所述第二信息上传至ERP管理系统。When the second information confirmation information is acquired, the first information and the second information are uploaded to the ERP management system.

作为本发明的进一步改进,获取货车的第一信息的步骤,包括如下步骤:As a further improvement of the present invention, the step of obtaining the first information of the truck includes the following steps:

获取货车的车牌信息和第一重量信息;Obtain the license plate information and first weight information of the truck;

将车牌信息和第一重量信息进行关联绑定。The license plate information and the first weight information are associated and bound.

作为本发明的进一步改进,在货车到达厂区之前,还包括如下步骤:As a further improvement of the present invention, before the truck arrives at the factory, the following steps are also included:

获取货车的货车预约登记信息,所述货车预约登记信息包括:车牌信息、公司名称信息、货物名称信息、作业人员信息和运货单信息;Obtain the truck reservation registration information of the truck, where the truck reservation registration information includes: license plate information, company name information, cargo name information, operator information and waybill information;

在预约登记信息审批通过时,将审批通过信息发送至智能终端设备。When the reservation registration information is approved and approved, the approval approval information is sent to the smart terminal device.

作为本发明的进一步改进,获取到第一信息确认信息的步骤,包括如下步骤:As a further improvement of the present invention, the step of obtaining the first information confirmation information includes the following steps:

通过车牌信息,将第一重量信息与预约登记信息进行关联;Associate the first weight information with the reservation registration information through the license plate information;

所述第一信息确认信息在货车司机确认所述第一重量信息、所述预约信息无误时发出。The first information confirmation information is sent when the truck driver confirms that the first weight information and the reservation information are correct.

作为本发明的进一步改进,本发明还包括步骤:As a further improvement of the present invention, the present invention also comprises steps:

在货车到达厂区时,获取若干货车的图片信息。When the truck arrives at the factory, obtain the picture information of several trucks.

作为本发明的进一步改进,所述第二信息包括:车牌信息和第二重量信息;As a further improvement of the present invention, the second information includes: license plate information and second weight information;

获取到第二信息确认信息的步骤,包括如下步骤:The step of acquiring the second information confirmation information includes the following steps:

作业人员对车牌信息、第二重量信息信息核实后,通过智能终端设备发出第二信息确认信息。After verifying the license plate information and the second weight information, the operator sends the second information confirmation information through the intelligent terminal device.

作为本发明的进一步改进,在进行货物处理的步骤中,若需要进行多次货物处理,则在第一次货物处理完毕后,获取货车的第二信息;As a further improvement of the present invention, in the step of cargo processing, if multiple cargo processing needs to be performed, the second information of the truck is obtained after the first cargo processing is completed;

货车重新返回至货物处理点,在获取到第一信息确认信息后,被允许进行货物处理;The truck returns to the cargo handling point, and is allowed to handle the cargo after obtaining the first confirmation information;

循环直至货物处理完毕。Loop until the goods are processed.

作为本发明的进一步改进,在货物处理完毕后,还包括如下步骤:As a further improvement of the present invention, after the goods are processed, the following steps are also included:

获取货物的当前位置信息;Get the current location information of the goods;

获取货物处理人员信息;Obtain cargo handler information;

获取时间信息;get time information;

将所述位置信息、所述处理人员信息、所述时间信息发送至ERP管理系统。Send the location information, the processing personnel information, and the time information to the ERP management system.

本发明的第二个方面,提供了一种多作业区信息实时联通智能物资监管系统,用于实现上述的多作业区信息实时联通智能物资监管方法,其包括:信息获取装置、智能终端设备、出入管理模块;In a second aspect of the present invention, a multi-operation area information real-time communication intelligent material supervision system is provided, which is used to realize the above-mentioned multi-operation area information real-time communication intelligent material supervision method, which includes: an information acquisition device, an intelligent terminal device, Access management module;

所述信息获取装置与所述智能终端设备、所述出入管理模块连接;The information acquisition device is connected to the intelligent terminal device and the access management module;

所述信息获取装置、所述智能终端设备均与ERP管理系统连接。The information acquisition device and the intelligent terminal equipment are all connected with the ERP management system.

与现有技术相比,本发明具有以下有益效果:自动获取货车的第一信息和第二信息,避免信息受到篡改,同时,将货车的第一信息、第二信息上传至ERP系统,结合ERP系统中的数据,便于对货物进行管理。Compared with the prior art, the present invention has the following beneficial effects: the first information and the second information of the truck are automatically obtained to avoid the information being tampered with; at the same time, the first information and the second information of the truck are uploaded to the ERP system, and combined with the ERP system The data in the system is convenient for the management of goods.

附图说明Description of drawings

下面结合附图对本发明的具体实施方式作进一步详细的说明,其中:The specific embodiments of the present invention will be described in further detail below in conjunction with the accompanying drawings, wherein:

图1为发明所述所述多作业区信息实时联通智能物资监管方法的流程图。FIG. 1 is a flow chart of the method for real-time communication of intelligent materials with multi-operation area information according to the invention.

具体实施方式Detailed ways

以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, but not to limit the present invention.

实施例1Example 1

本实施例结合物资出厂(需要称重的情况下)对多作业区信息实时联通智能物资监管方法进行详细说明,物资出厂模式中,包括的货物有:玻璃、麦渣、污土、二氧化碳、酒液、废旧物资回收等,如图1所示,该方法包括步骤:This embodiment describes in detail the method for real-time interconnection of intelligent material supervision with multi-working area information in conjunction with the delivery of materials (when weighing is required). The goods included in the material delivery mode include: glass, wheat residue, dirt, carbon dioxide, wine As shown in Figure 1, the method includes the steps:

S101、获取货车的货车预约登记信息,所述货车预约登记信息包括:车牌信息、公司名称信息、货物名称信息、作业人员信息和运货单信息;预约登记信息由货车司机在进入厂区前,通过智能终端设备输入,智能终端可以为手机。S101. Obtain the truck reservation registration information of the truck, where the truck reservation registration information includes: license plate information, company name information, cargo name information, operator information, and waybill information; Smart terminal device input, the smart terminal can be a mobile phone.

S102、在预约登记信息审批通过时,将审批通过信息发送至手机,告知司机已经通过审批。S102 , when the reservation registration information is approved, send the approval information to the mobile phone to inform the driver that the approval has been passed.

S103、货车进入厂区的门岗处时,获取货车的第一信息;第一信息包括:车牌信息和第一重量信息;此时货车应当是空车进入,故第一重量为空车时的重量。S103. When the truck enters the gate of the factory, obtain the first information of the truck; the first information includes: license plate information and first weight information; at this time, the truck should enter empty, so the first weight is the weight of the empty truck.

优选地,在货车达到厂区的门岗处时,还可以获取若干货车的图片信息,如货车的前、后、左、右四个方向上的图片信息,由门卫对货车进行进一步地账物一致核对工作。Preferably, when the truck arrives at the gate of the factory area, the picture information of several trucks can also be obtained, such as the picture information of the front, rear, left and right directions of the truck, and the gate guard will further check the goods in accordance with the goods of the truck. Work.

S102、货车达到装货区时,作业人员通过智能终端设备输入车牌信息,获取货车最近一次的重量信息,确认该货车已经通过称重操作,如货车没有进行称重操作,则作业人员要求货车回到门岗处进行重新称重,同时,在智能终端设备中选择运货单信息,关联出预约信息,由货车司机进行确认,包括公司名称信息、货物名称信息、作业人员信息和运货单信息等信息,在获取到第一信息确认信息后,被允许进行货物处理;所述第一信息确认信息在货车司机确认所述第一重量信息、所述预约信息无误时发出,确认方式可以为在智能终端设备上进行确认或者签名。S102. When the truck reaches the loading area, the operator enters the license plate information through the intelligent terminal device, obtains the latest weight information of the truck, and confirms that the truck has passed the weighing operation. If the truck has not been weighed, the operator asks the truck to return Go to the gate for re-weighing, and at the same time, select the waybill information in the smart terminal device, associate the reservation information, and the truck driver will confirm it, including company name information, cargo name information, operator information, and waybill information, etc. After obtaining the first information confirmation information, cargo processing is allowed; the first information confirmation information is sent when the truck driver confirms that the first weight information and the reservation information are correct, and the confirmation method can be in the intelligent Confirm or sign on the terminal device.

S103、在货物装车完毕后,货车行驶至门岗处,准备离开厂区,此时,获取货车的第二信息;第二信息包括车牌信息和第二重量信息,仓管员在智能终端设备上对运货单信息进行刷新,进而保存货车的第二重量信息,第二重量信息为货车完成货物装载后的重量。S103. After the goods are loaded, the truck drives to the gate and prepares to leave the factory. At this time, second information of the truck is obtained; the second information includes the license plate information and the second weight information. The waybill information is refreshed, and then the second weight information of the truck is stored, and the second weight information is the weight of the truck after the goods are loaded.

若同一辆货车需要运送两种以上的物资时,那么在本步骤之后,货车重新回到步骤S103,对货车进行重新称重,即循环步骤S102~步骤S103,直至把完成所有货物的装载。If the same truck needs to transport more than two kinds of materials, then after this step, the truck returns to step S103 to re-weigh the truck, ie, steps S102 to S103 are repeated until all the goods are loaded.

S104、在获取到第二信息确认信息时,将所述第一信息、所述第二信息上传至ERP管理系统。具体而言,货车没有装载货物前的重量、完成货物装载后的重量,均记录到ERP系统中。S104. When the second information confirmation information is obtained, upload the first information and the second information to the ERP management system. Specifically, the weight of the truck before loading the goods and the weight after loading the goods are recorded in the ERP system.

进一步地,第一信息还包括:货车的进厂时间,第二信息还包括:货车的出厂时间,根据进厂时间和出厂时间,计算出货车实际在工厂内的停留时间,货车的出厂时间、进厂时间、停留时间可存储在出入管理模块;若停留时间过长,可通过报警的方式提醒货车。Further, the first information further includes: the arrival time of the truck, and the second information further includes: the delivery time of the truck, according to the arrival time and the delivery time, calculate the actual stay time of the truck in the factory, the delivery time of the truck, The entry time and stay time can be stored in the access management module; if the stay time is too long, the truck can be reminded by an alarm.

最后,由于ERP系统存储有物料的采购信息或者货物的出库信息等,所以ERP系统通过该些信息,可按需要产生日、周、月、季度、年度、客户公司、物资类型等报表。Finally, because the ERP system stores material procurement information or goods outbound information, etc., the ERP system can generate daily, weekly, monthly, quarterly, annual, customer company, material type and other reports as needed through this information.

本实施例还包括无需称重车辆模式,包括步骤:This embodiment also includes a no-weighing vehicle mode, including the steps:

车辆在进厂门岗处时,获取车辆车牌信息、车辆进厂时间,将车牌信息以及车辆进厂时间上传至ERP系统中;When the vehicle enters the factory gate, obtain the vehicle license plate information and the vehicle entering time, and upload the license plate information and the vehicle entering time to the ERP system;

员工车辆、私家车、公务车出厂时,获取车牌信息、车辆出厂时间,并上传到上传到出入管理模块;实现车辆进出厂时间管理。When employee vehicles, private cars, and official vehicles leave the factory, obtain license plate information and vehicle delivery time, and upload them to the access management module; realize the management of vehicle access and delivery time.

回瓶、成品车、卸回瓶装成品这几类车辆,不进进行称重,车辆进入作业区,作业人员按原操作在智能终端设备上进行操作,单据信息自动同步到出入管理模块。Vehicles such as bottle return, finished vehicle, and unloaded bottled finished products are not weighed. The vehicles enter the operation area. The operators operate on the intelligent terminal equipment according to the original operation, and the document information is automatically synchronized to the access management module.

出厂时,获取车牌显示相关必要信息,车辆装载与单据最终状态一致则予以放行,否则不予放行。When leaving the factory, obtain the necessary information about the license plate display, and release the vehicle if the loading of the vehicle is consistent with the final state of the document, otherwise it will not be released.

此外,为了选车牌方便,员工车辆、私家车、公务车(以及大部分回瓶、成品车、回瓶装成品车),不需要进行称重,故无需显示在智能终端设备中,因此,减少了智能终端设备中的选择列表,便于快速选出目标车牌,减少出错概率;即以地磅车牌识别为选择项。若车辆已出厂也不再显示。若同一辆车出厂后第二次进厂,按重新入厂模式。In addition, in order to facilitate the selection of license plates, employee vehicles, private cars, official vehicles (and most of the bottled, finished cars, and bottled finished cars) do not need to be weighed, so they do not need to be displayed in the smart terminal device, thus reducing the number of The selection list in the intelligent terminal device is convenient to quickly select the target license plate and reduce the probability of errors; that is, the identification of the license plate of the weighbridge is an option. It is no longer displayed if the vehicle has been shipped from the factory. If the same car enters the factory for the second time after leaving the factory, press the re-entering mode.

实施例2Example 2

本实施例结合物资进厂(需要称重的情况下)对多作业区信息实时联通智能物资监管方法进行详细说明,物资进厂模式中,包括的货物有:大米、麦芽、淀粉、酒精等,如图1所示,该方法包括步骤:This embodiment describes in detail the method for real-time communication of intelligent materials for multi-operation area information in conjunction with materials entering the factory (when weighing is required). As shown in Figure 1, the method includes the steps:

S101、获取货车的货车预约登记信息,所述货车预约登记信息包括:车牌信息、公司名称信息、货物名称信息、作业人员信息和运货单信息;预约登记信息由货车司机在进入厂区前,通过智能终端设备输入,智能终端可以为手机。S101. Obtain the truck reservation registration information of the truck, where the truck reservation registration information includes: license plate information, company name information, cargo name information, operator information, and waybill information; Smart terminal device input, the smart terminal can be a mobile phone.

S102、在预约登记信息审批通过时,将审批通过信息发送至手机,告知司机已经通过审批。S102 , when the reservation registration information is approved, send the approval information to the mobile phone to inform the driver that the approval has been passed.

S103、货车进入厂区的门岗处时,获取货车的第一信息;第一信息包括:车牌信息和第一重量信息;此时货车应当是装载着货物进入,故第一重量为货车装载货物时的重量。S103, when the truck enters the gate of the factory, obtain the first information of the truck; the first information includes: license plate information and first weight information; at this time, the truck should enter with cargo, so the first weight is the value when the truck is loaded with cargo weight.

优选地,在货车达到厂区的门岗处时,还可以获取若干货车的图片信息,如货车的前、后、左、右四个方向上的图片信息,由门卫对货车进行进一步地账物一致核对工作。Preferably, when the truck arrives at the gate of the factory area, the picture information of several trucks can also be obtained, such as the picture information of the front, rear, left and right directions of the truck, and the gate guard will further check the goods in accordance with the goods of the truck. Work.

S102、货车达到卸货区时,仓管员通过智能终端设备输入车牌信息,获取货车最近一次的重量信息,确认该货车已经通过称重操作,如货车没有进行称重操作,则仓管员要求货车回到门岗处进行重新称重,同时,在智能终端设备中选择运货单信息,关联出预约信息,由货车司机进行确认,包括公司名称信息、货物名称信息、作业人员信息和运货单信息等信息,在获取到第一信息确认信息后,被允许进行货物处理;所述第一信息确认信息在货车司机确认所述第一重量信息、所述预约信息无误时发出,确认方式可以为在智能终端设备上进行确认或者签名。S102. When the truck reaches the unloading area, the warehouse keeper enters the license plate information through the intelligent terminal device, obtains the latest weight information of the truck, and confirms that the truck has passed the weighing operation. If the truck has not been weighed, the warehouse keeper will ask the truck Return to the gate for re-weighing, and at the same time, select the waybill information in the intelligent terminal device, associate the reservation information, and confirm by the truck driver, including company name information, cargo name information, operator information and waybill information and other information, after obtaining the first information confirmation information, cargo processing is allowed; the first information confirmation information is sent when the truck driver confirms that the first weight information and the reservation information are correct, and the confirmation method can be at Confirm or sign on the smart terminal device.

S103、在货物卸车完毕后,货车行驶至门岗处,准备离开厂区,此时,获取货车的第二信息;第二信息包括车牌信息和第二重量信息,仓管员在智能终端设备上对运货单信息进行刷新,进而保存货车的第二重量信息,第二重量信息为货车空车时的重量。S103. After the unloading of the goods is completed, the truck drives to the gate post and prepares to leave the factory area. At this time, the second information of the truck is obtained; the second information includes the license plate information and the second weight information, and the warehouse keeper checks the transport on the intelligent terminal device. The manifest information is refreshed, and then the second weight information of the truck is stored, and the second weight information is the weight of the truck when it is empty.

若同一辆货车需要运送两种以上的物资时,那么在本步骤之后,货车重新回到步骤S103,对货车进行重新称重,即循环步骤S102~步骤S103,直至把完成所有货物的卸车。If the same truck needs to transport more than two kinds of materials, then after this step, the truck returns to step S103 to re-weigh the truck, that is, steps S102 to S103 are repeated until all the goods are unloaded.

S104、在获取到第二信息确认信息时,将所述第一信息、所述第二信息上传至ERP管理系统。具体而言,货车装载货物时的重量、完成货物卸车后的重量,均记录到ERP系统中。S104. When the second information confirmation information is obtained, upload the first information and the second information to the ERP management system. Specifically, the weight of the truck loaded with goods and the weight of the goods after unloading are all recorded in the ERP system.

进一步地,第一信息还包括:货车的进厂时间,第二信息还包括:货车的出厂时间,根据进厂时间和出厂时间,计算出货车实际在工厂内的停留时间,货车的出厂时间、进厂时间、停留时间可存储在出入管理模块;若停留时间过长,可通过报警的方式提醒货车。Further, the first information further includes: the arrival time of the truck, and the second information further includes: the delivery time of the truck, according to the arrival time and the delivery time, calculate the actual stay time of the truck in the factory, the delivery time of the truck, The entry time and stay time can be stored in the access management module; if the stay time is too long, the truck can be reminded by an alarm.

最后,由于ERP系统存储有物料的采购信息或者货物的出库信息等,所以ERP系统通过该些信息,可按需要产生日、周、月、季度、年度、客户公司、物资类型等报表。Finally, because the ERP system stores material procurement information or goods outbound information, etc., the ERP system can generate daily, weekly, monthly, quarterly, annual, customer company, material type and other reports as needed through this information.

实施例3Example 3

本实施例提供了一种多作业区信息实时联通智能物资监管系统,用于实现实施例1中的多作业区信息实时联通智能物资监管方法,其包括:信息获取装置、智能终端设备、出入管理模块;信息获取装置与智能终端设备、出入管理模块连接;信息获取装置、智能终端设备均与ERP管理系统连接智能终端设备可以为平板电脑或者收据。This embodiment provides a multi-work area information real-time communication intelligent material supervision system, which is used to realize the multi-work area information real-time connection and intelligent material supervision method in Embodiment 1, which includes: an information acquisition device, an intelligent terminal device, and an access management system. module; the information acquisition device is connected to the intelligent terminal device and the access management module; the information acquisition device and the intelligent terminal device are both connected to the ERP management system. The intelligent terminal device can be a tablet computer or a receipt.

具体地,信息获取装置设置在进厂区域,包括:电子汽车衡自动称重装置,用于对汽车进行称重以及车牌信息的获取。信息获取装置、智能终端设备可通过以下方式实现将数据传输至ERP系统:1、要求用户MIS系统采用MS SQL Server数据库服务器,用户MIS系统的数据库服务器上给称重系统开放权限,建立一张交换数据表(表结构由MT提供),接口软件会自将新增的称重数据保存到交换数据表中;2、AVS称重系统在称重服务器上建立一个交换数据文件,格式xml(数据存放格式由MTCN制定),系统开放该文件的访问权限给用户MIS系统,用户MIS系统可以定期导入该文件,实现称重数据的集成,接口软件自动将新增称重数据保存到交换文件中。Specifically, the information acquisition device is arranged in the factory entry area, including: an electronic truck scale automatic weighing device, which is used for weighing the vehicle and acquiring license plate information. The information acquisition device and intelligent terminal equipment can transmit data to the ERP system in the following ways: 1. The user MIS system is required to use the MS SQL Server database server, and the database server of the user MIS system gives the weighing system open authority, and establishes an exchange Data table (table structure is provided by MT), the interface software will automatically save the newly added weighing data to the exchange data table; 2. AVS weighing system establishes an exchange data file on the weighing server, in the format xml (data storage The format is formulated by MTCN), the system opens the access authority of the file to the user MIS system, the user MIS system can import the file regularly to realize the integration of weighing data, and the interface software automatically saves the newly added weighing data to the exchange file.

每台电子汽车衡现场还安装有车辆红外光栅装置、红绿灯、车牌自动识别系统、摄像监控设备、道闸、语音等设备。实现称重过程的自动化管理,规范称重过程,保证计量结果的准确、真实、有效。采用语音功能,可以在称重过程中自动提示司机上下秤,防作弊报警提示,基于此,可以实现无人值守的称重,节省人力。Each electronic truck scale is also equipped with vehicle infrared grating device, traffic lights, automatic license plate recognition system, camera monitoring equipment, road gate, voice and other equipment. Realize the automatic management of the weighing process, standardize the weighing process, and ensure the accuracy, authenticity and effectiveness of the measurement results. Using the voice function, the driver can be automatically prompted to get on and off the scale during the weighing process, and an alarm to prevent cheating can be prompted. Based on this, unattended weighing can be realized and manpower can be saved.

采用电子汽车衡,与传统的设备相比,能够避免司机采用遥控器等技术手段进行作弊,改变计量结果,能大大地提高计量的准确性。Using electronic truck scales, compared with traditional equipment, can prevent drivers from cheating by using remote control and other technical means, change the measurement results, and greatly improve the accuracy of measurement.

此外,信电子汽车衡中的摄像监控设备,用于监控称重区域的现场情况,便于抓拍称重过程情况及协助司磅员观察称重情况。In addition, the camera monitoring equipment in the Xindian truck scale is used to monitor the on-site situation of the weighing area, which is convenient for capturing the weighing process and assisting the weighing operator to observe the weighing situation.

综合上述实施例1~实施例3可知,本发明具有以下技术效果:It can be known from the above-mentioned Embodiments 1 to 3 that the present invention has the following technical effects:

1、利用车牌识别技术,识别车牌,车辆自动录入系统,不可修改;1. Use the license plate recognition technology to identify the license plate, and the vehicle is automatically entered into the system, which cannot be modified;

2、地磅实现无人称重模式,视频监控、拍照、红外光栅技术、防遥控作弊技术、防夹带技术等确保称重过程无纸化、无人化,车牌绑定地磅重量,记录车辆上称到下称全过程纪录监控拍照,一经上传,不可修改,不可丢失,双数据库备份保存。2. The platform scale realizes the unmanned weighing mode, video surveillance, photography, infrared grating technology, anti-remote cheating technology, anti-entrainment technology, etc. to ensure that the weighing process is paperless and unmanned, the license plate is bound to the weight of the platform scale, and the vehicle weighs Hereinafter referred to as the whole process record monitoring photo, once uploaded, it cannot be modified or lost, and the double database backup is saved.

3、作业区使用平板电脑,门岗、地磅作业区数据交互,以及与现有的ERP系统数据无缝对接;作业区人员只持平板电脑勾或手机选动作,每张工单绑定作业人员,可追溯,责任到人,系统对作业人员形成巨大威慑力,有助于作业人员提高工作责任心,杜绝了与车辆勾结损害公司行为,以及司机作弊行为。3. Tablet computers are used in the operation area, data exchange between gate guards and weighbridge operation areas, and seamless connection with the existing ERP system data; personnel in the operation area only use tablet computers or mobile phones to select actions, and each work order is bound to the operator, It can be traced back and the responsibility belongs to the person. The system forms a huge deterrent force for the operators, which helps the operators to improve their sense of responsibility, and eliminates the behavior of colluding with vehicles to damage the company and the cheating of drivers.

以上仅为本申请的较佳实施例,并不用以限制本申请,凡在本申请的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本申请的保护范围之内。The above are only preferred embodiments of the present application and are not intended to limit the present application. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application. Inside.

Claims (9)

1. A multi-operation-area information real-time communication intelligent material supervision method is characterized by comprising the following steps:

when a truck arrives at a factory area, acquiring first information of the truck;

when the truck reaches a cargo processing point, after the first information confirmation information is acquired, allowing cargo processing to be carried out;

after the goods are processed, second information of the truck is obtained;

and uploading the first information and the second information to an ERP management system when second information confirmation information is acquired.

2. The intelligent material supervision method for real-time communication of information in multiple operation areas according to claim 1, wherein the step of acquiring the first information of the truck comprises the following steps:

acquiring license plate information and first weight information of a truck;

and associating and binding the license plate information and the first weight information.

3. The intelligent material supervision method with real-time communication of multi-operation-area information according to claim 1, characterized by further comprising the following steps before the truck arrives at the factory:

acquiring truck appointment registration information of a truck, wherein the truck appointment registration information comprises: license plate information, company name information, cargo name information, operator information and freight note information;

and when the examination and approval of the reservation and registration information pass, sending the examination and approval passing information to the intelligent terminal equipment.

4. The intelligent material supervision method for real-time information communication in multiple operation areas according to claim 2, wherein the step of acquiring the first information confirmation information comprises the steps of:

associating the first weight information with reservation registration information through the license plate information;

and the first information confirmation information is sent out when the truck driver confirms that the first weight information and the reservation information are correct.

5. The method for supervising the multi-operation-area information real-time communication intelligent materials according to any one of claims 1 to 4, further comprising the steps of:

when the truck arrives at a factory area, the picture information of a plurality of trucks is obtained.

6. The method for supervising the multi-operation-area information real-time communication intelligent materials according to claim 1, wherein the second information comprises: license plate information and second weight information;

the step of acquiring the second information confirmation information includes the following steps:

and after the license plate information and the second weight information are verified by the operator, second information confirmation information is sent out through the intelligent terminal equipment.

7. The method for supervising the information real-time communication intelligent materials in the multiple operation areas according to claim 1, wherein in the step of cargo processing, if cargo processing needs to be performed for multiple times, second information of a truck is acquired after the first cargo processing is finished;

the truck returns to the cargo processing point again, and after the first information confirmation information is obtained, the cargo processing is allowed to be carried out;

and circulating until the goods are processed.

8. The method for supervising the multi-operation-area information real-time communication intelligent materials according to claim 1 or 6, wherein after the goods are processed, the method further comprises the following steps:

acquiring current position information of the goods;

acquiring information of cargo handlers;

acquiring time information;

and sending the position information, the processor information and the time information to an ERP management system.

9. The system for supervising the intelligent materials in real time communication of the information in the multiple operation areas is characterized by being used for realizing the method for supervising the intelligent materials in real time communication of the information in the multiple operation areas according to any one of claims 1 to 8, and comprising the following steps of: the system comprises an information acquisition device, intelligent terminal equipment and an access management module;

the information acquisition device is connected with the intelligent terminal equipment and the access management module;

the information acquisition device and the intelligent terminal equipment are connected with an ERP management system.

CN202210787153.XA 2022-07-05 2022-07-05 Multi-operation area information real-time interconnection intelligent material supervision method and system Pending CN115081915A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210787153.XA CN115081915A (en) 2022-07-05 2022-07-05 Multi-operation area information real-time interconnection intelligent material supervision method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210787153.XA CN115081915A (en) 2022-07-05 2022-07-05 Multi-operation area information real-time interconnection intelligent material supervision method and system

Publications (1)

Publication Number Publication Date
CN115081915A true CN115081915A (en) 2022-09-20

Family

ID=83258050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210787153.XA Pending CN115081915A (en) 2022-07-05 2022-07-05 Multi-operation area information real-time interconnection intelligent material supervision method and system

Country Status (1)

Country Link
CN (1) CN115081915A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101587333A (en) * 2009-07-03 2009-11-25 西安众泰电子科技有限公司 Intelligent control device system for mineral material transportation and sale flow and system application method
CN101718982A (en) * 2009-11-23 2010-06-02 周巍 System and method for integrally controlling loading, transportation and unloading
CN106779566A (en) * 2017-01-11 2017-05-31 总信(北京)信息技术有限公司 A kind of goods and materials managing and control system and its method
CN110084551A (en) * 2019-04-23 2019-08-02 深圳市艾赛克科技有限公司 Material intelligent shipping systems
CN110705938A (en) * 2019-07-03 2020-01-17 苏州恒赛特自动化科技有限公司 Intelligent logistics system
CN111199374A (en) * 2019-12-31 2020-05-26 河南云煤网网络科技有限责任公司 Goods in-and-out-of-factory identity recognition and metering settlement method and system
CN113689092A (en) * 2021-08-09 2021-11-23 山东钢铁集团日照有限公司 A method of automatic queuing and number calling for vehicles entering the door based on the technology of the Internet of Vehicles
CN114037588A (en) * 2021-11-02 2022-02-11 常州皓鸣信息科技有限公司 A kind of truck scale remote centralized measurement control system and method
CN114394445A (en) * 2022-01-13 2022-04-26 青岛杰瑞工控技术有限公司 Port granary intelligent loading and unloading system based on industrial internet
CN114429329A (en) * 2022-01-20 2022-05-03 道达信息科技(苏州)有限公司 Warehouse automatic distribution and delivery management system and method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101587333A (en) * 2009-07-03 2009-11-25 西安众泰电子科技有限公司 Intelligent control device system for mineral material transportation and sale flow and system application method
CN101718982A (en) * 2009-11-23 2010-06-02 周巍 System and method for integrally controlling loading, transportation and unloading
CN106779566A (en) * 2017-01-11 2017-05-31 总信(北京)信息技术有限公司 A kind of goods and materials managing and control system and its method
CN110084551A (en) * 2019-04-23 2019-08-02 深圳市艾赛克科技有限公司 Material intelligent shipping systems
CN110705938A (en) * 2019-07-03 2020-01-17 苏州恒赛特自动化科技有限公司 Intelligent logistics system
CN111199374A (en) * 2019-12-31 2020-05-26 河南云煤网网络科技有限责任公司 Goods in-and-out-of-factory identity recognition and metering settlement method and system
CN113689092A (en) * 2021-08-09 2021-11-23 山东钢铁集团日照有限公司 A method of automatic queuing and number calling for vehicles entering the door based on the technology of the Internet of Vehicles
CN114037588A (en) * 2021-11-02 2022-02-11 常州皓鸣信息科技有限公司 A kind of truck scale remote centralized measurement control system and method
CN114394445A (en) * 2022-01-13 2022-04-26 青岛杰瑞工控技术有限公司 Port granary intelligent loading and unloading system based on industrial internet
CN114429329A (en) * 2022-01-20 2022-05-03 道达信息科技(苏州)有限公司 Warehouse automatic distribution and delivery management system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
赵云龙等: "矿用到货自动登记系统设计", 《共矿自动化》, vol. 43, no. 12, 10 December 2017 (2017-12-10), pages 26 - 31 *

Similar Documents

Publication Publication Date Title
CN103559605B (en) 2014-08-06 Intelligent depot output-input system of digital grain depot
CN101609337B (en) 2011-03-30 Control method of unattended system for fuel in and out of thermal power plant
CN107358383B (en) 2021-03-26 Logistics freight system
CN112529592A (en) 2021-03-19 Novel one-card unattended management system
CN112633797A (en) 2021-04-09 Intelligent management system and method for port cargo operation
CN212931612U (en) 2021-04-09 Weighbridge management system suitable for building site material transportation
JP2001520610A (en) 2001-10-30 Container monitoring system and method
KR102368084B1 (en) 2022-02-28 Transit Management System
LU507791B1 (en) 2024-09-23 Logistics station vehicle transportation management method and on-site weighing apparatus
CN110458307A (en) 2019-11-15 Realize the system and method for intelligent purchasing management
CN111401806B (en) 2023-04-07 Automatic material information management system
CN110610335A (en) 2019-12-24 Intelligent purchase and sale management system for chemical enterprises
CN115481989B (en) 2023-04-07 Unattended material receiving and selling system of concrete mixing plant and working method
CN107121182A (en) 2017-09-01 A kind of unattended automatic weighing system in mine
CN117217698B (en) 2024-04-16 Unmanned automatic weighing system of code-through truck scale
CN112634115A (en) 2021-04-09 Intelligent weighing system and method for port goods
CN112101906A (en) 2020-12-18 Intelligent coal mine management system
CN111861331A (en) 2020-10-30 Intelligent management system for hazardous chemical substance logistics warehouse entry and exit
TW548568B (en) 2003-08-21 System and method for controlling and monitoring stocking and shipping
US20050261917A1 (en) 2005-11-24 Electronic waste management system
CN114037588A (en) 2022-02-11 A kind of truck scale remote centralized measurement control system and method
WO2025002175A1 (en) 2025-01-02 Power plant fly ash vehicle management method
JP4361070B2 (en) 2009-11-11 Waste management system
CN115081915A (en) 2022-09-20 Multi-operation area information real-time interconnection intelligent material supervision method and system
CN116342027A (en) 2023-06-27 Digital storage system and storage method for bulk raw materials

Legal Events

Date Code Title Description
2022-09-20 PB01 Publication
2022-09-20 PB01 Publication
2022-10-11 SE01 Entry into force of request for substantive examination
2022-10-11 SE01 Entry into force of request for substantive examination